100%
Completed August 2023
New intake, about 400 metres of pipeline and storage tanks for 62 households in Navuloa.
$82,500approved budget
62households benefiting
FY2022-23financial year
October 2022started
August 2023completed
Rural and Outer Islands Programmeprogramme
This project is made up for the prototype. In the delivered portal, questions about a project go to its Divisional Office, quoting the reference RDP-2023-E-0012.