100%
Completed October 2023
New intake, about 1150 metres of pipeline and storage tanks for 40 households in Togoru Settlement.
$70,000approved budget
40households benefiting
FY2022-23financial year
May 2023started
October 2023completed
Disaster Rehabilitation Programmeprogramme
This project is made up for the prototype. In the delivered portal, questions about a project go to its Divisional Office, quoting the reference RDP-2023-C-0017.