100%
Completed March 2021
Concrete footbridge and approach paths giving Nawau safe all-weather access to school, market and the main road.
$302,500approved budget
189households benefiting
FY2019-20financial year
April 2020started
March 2021completed
Community Access Roads, Footpaths and Footbridgesprogramme
This project is made up for the prototype. In the delivered portal, questions about a project go to its Divisional Office, quoting the reference RDP-2020-W-0006.